Company overview
Ridgeline Crossing Partners is a special-purpose project company formed to replace the 1960s-era Ridgeline River bridge, a 1.2-mile, four-lane interstate crossing that a state department of transportation (the State, rated AA−) has classified as structurally deficient. Under a 35-year design-build-finance-operate-maintain concession, the project company builds the new bridge over about three years, then operates and maintains it for 32 years and hands it back in specified condition. There are no tolls: the State pays an annual availability payment if the bridge is open and meets performance standards.
The maximum availability payment is $88.0M in the first operating year, with 60% of it indexed to inflation (assumed 2.0% a year) and 40% fixed. The State deducts from the payment for lane closures and missed performance standards; deductions can reach 100% of the payment. Payments are subject to annual appropriation by the state legislature, with a non-appropriation termination right that requires the State to compensate senior debt in full.
Construction is subcontracted to the Arcadia–Harlow joint venture under a fixed-price, date-certain design-build contract of $860M. Operations and maintenance are subcontracted to an affiliate of one of the equity sponsors. The project company is asking for $780M of senior secured, fixed-rate debt with a 28-year amortization after completion, sculpted to a 1.30x minimum debt service coverage ratio in the sponsor's base case.
The IC question: with no traffic risk, does the package of contractor security, reserves and covenants protect the lender through construction, lifecycle spikes and a period of poor performance, and is 135 bp over Treasuries enough?
Your memo should answer
- 01Would you lend on these terms? State your recommendation and the conditions or changes you would require.
- 02Is the construction security package enough to cover a 12-month delay or a 15% cost overrun, and what happens if the contractor itself fails?
- 03Assess the debt sizing: minimum and average DSCR, loan life coverage, the tail, and whether 1.30x is enough given the lifecycle spikes.
- 04Build a downside combining deductions, higher operating costs and lifecycle overruns. When do the 1.15x lock-up and 1.05x default tests trip, and how far can CFADS fall before default?
- 05What do appropriation risk and the termination regime mean for the lender in each termination scenario?
- 06Is 135 bp over Treasuries enough for this risk, and what would you change in the documents?
Financials ($M)
| Op year 1 (2030) | Op year 5 | Op year 10 | Op year 20 | Op year 30 | |
|---|---|---|---|---|---|
| Availability payment, before deductions | 88.0 | 92.4 | 98.3 | 112.1 | 129.0 |
| Operations and maintenance | 9.0 | 9.9 | 11.2 | 14.4 | 18.4 |
| Insurance and project company costs | 3.0 | 3.3 | 3.7 | 4.8 | 6.1 |
| Lifecycle reserve contributions | 4 | 5 | 12 | 14 | 6 |
| Cash flow available for debt service | 72.0 | 74.1 | 71.3 | 78.9 | 98.4 |
| Senior debt service | 52.0 | 53.5 | 54.0 | 56.0 | 0.0 |
| DSCR (sponsor base case) | 1.38x | 1.39x | 1.32x | 1.41x | n/a (debt repaid) |
Term sheet
- Facility
- $780M senior secured fixed-rate term loan to Ridgeline Crossing Partners (project company); drawn during construction
- Tenor and amortization
- 31 years from close: 3-year construction availability, then 28-year amortization sculpted to the sponsor base case; 4-year tail before concession end
- Pricing
- Fixed 5.60% (30-year Treasury 4.25% + 135 bp); 0.75% upfront fee; make-whole call
- Pricing context
- Recent availability-payment P3 private placements rated BBB to BBB+ priced at Treasuries + 120 to 165 bp; projects with full construction risk at the wider end
- Sizing
- Minimum DSCR 1.30x and average 1.39x in the sponsor base case; loan life coverage ratio 1.42x
- Distribution lock-up and default
- Distributions to equity blocked below 1.15x historical and projected DSCR; event of default below 1.05x historical DSCR
- Reserves
- Debt service reserve of 6 months' debt service, funded at close; lifecycle reserve funded per the lifecycle plan; handback reserve from year 27
- Security
- First-priority lien on all project company assets, accounts and the concession agreement; direct agreements with the State, the design-build contractor and the O&M contractor
- Other terms
- Cash waterfall: O&M, senior debt service, DSRA, lifecycle reserve, lock-up test, then equity; no additional senior debt except permitted refinancing
Sources and uses ($M, construction period)
- Uses: design-build contract (fixed price)
- 860.0
- Uses: owner's and development costs
- 30.0
- Uses: construction contingency
- 25.0
- Uses: interest during construction
- 85.0
- Uses: financing fees
- 20.0
- Uses: debt service reserve funding
- 30.0
- Total uses
- 1,050.0
- Sources: senior debt
- 780.0
- Sources: sponsor equity (paid in pro rata with debt)
- 150.0
- Sources: State milestone payments during construction
- 120.0
- Total sources
- 1,050.0
Construction security package (design-build contract with the Arcadia–Harlow joint venture)
- Contract
- Fixed price $860M; date-certain substantial completion 36 months after notice to proceed
- Delay liquidated damages
- $150,000 per day, capped at 15% of the contract price ($129M)
- Letter of credit
- 10% of the contract price ($86M), from investment-grade banks
- Payment and performance bonds
- 50% of the contract price
- Parent guarantees
- Joint and several guarantees from both joint-venture parents
- Owner contingency
- $25M, about 3% of the design-build price
- Key exclusions
- Unforeseen river-bed geotechnical conditions above a $10M threshold are a shared risk with the State
Payment mechanism and deductions
- Availability payment
- $88.0M maximum in operating year 1; 60% indexed to inflation, 40% fixed
- Unavailability deductions
- Per lane-closure hour, weighted by time of day; peak-hour closure of all lanes can remove the full daily payment
- Performance deductions
- Points for missed maintenance and response standards; deductions capped at 5% of the annual payment before a default warning
- Deduction history on comparable State P3s
- About 0.5–1.5% of the annual payment in steady state; up to 4% in the first two operating years
- Appropriation
- Payments subject to annual legislative appropriation; non-appropriation lets the project company terminate with compensation covering senior debt in full
Termination compensation
- State default or convenience
- Senior debt outstanding plus breakage, and equity at a contractual return
- Force majeure
- Senior debt outstanding; equity receives its paid-in capital less distributions
- Project company default
- Adjusted estimated fair value of the contract after rebidding, capped at senior debt outstanding; no floor
- Handback
- Asset must meet residual-life standards at year 35; handback reserve funded from year 27; the State may withhold payments for shortfalls