Infrastructure loans finance long-lived assets such as roads, bridges, energy projects and social infrastructure. They're usually made to a special-purpose company that owns only the project, so the lender relies on the project's own cash flows, not a parent's balance sheet.
The debt is sized to the cash flow, not to a leverage multiple. The core question is: after operating costs and maintenance, how many times does cash cover debt service in every period, including the weakest one?
| Model | How the project is paid | Main revenue risk |
|---|---|---|
| Availability payment | A public authority pays a fixed amount if the asset is available and meets performance standards. | Deductions for unavailability, and the authority's ability to pay (appropriation risk). |
| Toll or demand-based | Users pay to use the asset. | Traffic volumes and ramp-up, which are hard to forecast. |
| Contracted | A long-term offtake or power purchase agreement. | Counterparty credit and contract terms. |
| Regulated | A regulator sets allowed returns. | Regulatory resets and political risk. |
| Metric | What it measures |
|---|---|
| CFADS | Cash flow available for debt service: revenue minus operating, maintenance and tax costs. |
| DSCR (minimum and average) | CFADS divided by scheduled principal and interest, period by period. The minimum matters most. |
| LLCR | Present value of CFADS over the loan's life divided by debt outstanding. |
| DSRA sizing | How many months of debt service the reserve account covers. |
| Tail | Years of contracted or expected cash flow left after the debt is repaid. |
| Deductions or traffic sensitivity | How far revenue can fall before DSCR hits lock-up or default levels. |
Illustrative numbers only. A project earns $60M a year of availability payments and spends $15M on operations and maintenance, so CFADS is $45M. Annual debt service is $33M.
The point
In project finance, the cushion is measured in coverage, not leverage. Always show how far cash flow can fall before each trigger.
Practice on the availability-payment bridge case in the library. Its model template runs an annual CFADS and debt build with sculpted debt service, coverage ratios, a combined operating stress and a construction delay test. For the core credit tabs, see How to build the credit model.
Educational only. Nothing in this guide is investment, legal or tax advice. Practice on a case, and never use an employer's confidential documents.